# Generator or grid: how to choose the power source?

> Power available on site, temporary grid connection in France up to 36 kVA or 250 kVA, generator or battery: in what order to choose the power source of an event.

Source: https://www.darkside-energy.com/en/did-you-know/generator-or-grid/ · Dark Side Energy · Updated: 2026-11-24

24 November 2026 · 3 min read

- The grid first: look at what the venue can supply, then at what a temporary connection can add.
- With Enedis, the French distribution network operator, a temporary connection is low voltage up to 250 kVA, with a threshold at 36 kVA. Above that, it moves to high voltage.
- When the grid is not enough: generator, battery pack, or both in a hybrid setup, sized from the power assessment.

Before ordering a generator, one question comes first: can the grid supply the power? This is our rule: we study the feasibility of a connection to the existing grid before using generators as the main source.

## 1. What the venue can already supply

A site connected to the grid has a [import capacity](https://www.darkside-energy.com/en/glossary/#puissance-de-soutirage): the maximum power it can draw, set by its contract. It tells you what the venue can supply without reinforcement. If the event's power assessment fits within it, the source is found.

## 2. What a temporary connection can add

In France, Enedis provides temporary connections for installations that are not permanent: construction sites, funfairs, fêtes, markets. They are short-term up to 28 days, long-term beyond.

| Power | Connection |
| --- | --- |
| Up to 36 kVA | Low voltage, three-phase above 12 kVA |
| From 36 to 250 kVA | Low voltage |
| Above 250 kVA | High voltage (HTA), with no short-term offer |

In three-phase 400 V, 36 kVA means 52 A per phase, the rating of a P17 63 A socket. 250 kVA means 361 A per phase, a Powerlock 400 A connection.

The request goes through an electricity supplier, which Enedis advises contacting 25 days before the power is needed. After the delivery point, the equipment is supplied and installed by the applicant: this is where the event's distribution starts.

## 3. When the grid is not enough

Remote site, insufficient power, limited or costly connection: power must then be produced on site. Three solutions, alone or combined:

- a generator, sized to the actual need: too big for its load, [it clogs up](https://www.darkside-energy.com/en/did-you-know/generator-light-load/);
- a [battery pack](https://www.darkside-energy.com/en/glossary/#pack-batterie), which powers the event without a combustion engine;
- both in a [hybrid setup](https://www.darkside-energy.com/en/glossary/#hybridation): the battery supplies low loads and covers the peaks, and the generator only starts when demand or recharging requires it.

Grid and generator can also be combined.

> The grid first, the generator second, and never bigger than the need.

Studying the connection before bringing out the generators is part of our [responsible energy](https://www.darkside-energy.com/en/responsible-energy/) approach.

To know whether the grid is enough, you first need the power to plan for: that is the role of the power assessment.

[Run a power assessment](https://www.darkside-energy.com/en/power-assessment/)

[French electrical authorisations: what do B0, BR, B2V and BC mean?](https://www.darkside-energy.com/en/did-you-know/electrical-authorisations/)

## A project? Let's talk power.

Venue, dates, known requirements: tell us about your event and we will get back to you quickly.